In brief

In brief

News from :

June 2020

Manche

In Flamanville and in the framework of the creation of vehicle recharge facilities in the car park of the nuclear power plant, EDF has entrusted SADE Télécom (Nord Agency) with the installation and electrical connection of 270 charging terminals (7 and 11 KW).

June 2020

Moselle

On behalf of Ascométal and for the creation of a discharge pipe for the WWTP outflow in Hagondange, SADE will lay 30m of gravitational discharge pipes (1000mm-diameter GRP & steel with GRP close-fit lining) and 2 reinforced concrete access pits.

June 2020

Gironde

Following several breaks on a 400m concrete collector in Audenge, the Bassin d’Arcachon Intermunicipal Authority (SIBA) has called on SADE to replace 275m of said collector and 125m of HDPE slip lining. In order to avoid heavy excavation works, SADE is recommending the use of HDPE slip lining for the entire concrete pipeline (i.e. 400m).

In Brittany and in the framework of a test phase with ENEDIS, the Rennes Regional Division (Brest Agency) will carry out technical studies for private user connections to the ENEDIS public network, subsequent connection (charged unit to a power pole) and the installation of corresponding meters.

May 2020

China

In Changzhou, ChangZhou SADE General Construction & Engineering, on behalf of Changzhou CGE Water Co., Ltd, will lay 29km of vertical water supply pipelines (20mm to 219mm-diameter) in addition to associated equipment (water gates, etc.).

May 2020

Val d’Oise

In the framework of the renewal of the water supply network pipelines in Cergy, Osny and Pontoise, CYO has entrusted SFDE Travaux (a SADE subsidiary) with the laying of 1,290m of pipelines (150mm and 200mm-diameter cast-iron), the creation of 55 junction extensions and 26 branch connections to existing pipes.

May 2020

Var

On behalf of ENEDIS and for a duration of 4 years, ETE Réseaux (a SADE subsidiary) will be carrying out studies and subsequent junction works for subscribers (individual & collective) to the electricity supply network across the department.

May 2020

Pas-de-Calais

In Wingles, INEOS STYROLUTION has entrusted SADE with the building of gravitational waste and industrial water networks in one of its sites. Works will consist in laying 71m of pipes (500mm-diameter carbon steel for industrial water and 500mm-diameter HDPE for wastewater) in addition to their connection via a 4x4m well at a depth of 6m.

May 2020

Ain

For the extension of the discharge network of the new WWTP in Replonges, the municipal authority has entrusted SOMEC (a SADE subsidiary) with the laying of 2,010m of pipelines (300mm-diameter polypropylene & cast-iron and 200mm-diameter HDPE), 2 suction pads and 2 water gates, in addition to 3,500m² of bilayer repairs

May 2020

Manche

For the securing of the water supply network to the Cargill production plant in Baupte, and on behalf of the Isthme du Cotentin joint water supply authority, SADE will be installing 5 civil engineering chambers (4x2x2m), and flow regulation equipment (flowmeter, stabiliser, valves and probes) and will be replacing the raw water well heads (flowmeter, pressure probe and surge control system, etc.).