• fr
  • en
  • es
  • En
  • Fr
  • Es
x
Logo
  • In brief
    • Profile
      • Key figures
      • Governance and Ethics
      • Certifications
    • Anchoring
      • International
      • France
    • Path
  • Business lines
    • Networks
      • Water
      • Energy
    • Infrastructure
      • Civil engineering
      • Underground works
  • Services and Solutions
    • Regional authorities
    • Industries
    • Major infrastructures
  • CSR: A Conviction
  • Innovation
  • References
  • Careers
    • Proud to be a pro at SADE
    • Job application
  • News
    • Current projects
  • Contact
  • En
    • Fr
    • Es
recherche
  • En
  • Fr
  • Es

Current projects

Back to all projects

Making sure fire-fighting water storage is compliant

July 20, 2021

… to protect the environment at Collins Aérospace

As part of its efforts to develop the industrial market, the Paris Regional Division won a contract with Collins Aérospace in Antony (in the Hauts-de-Seine department)

The site specialises in the maintenance and manufacture of fire-protection systems for helicopters, tanks and aeroplanes. An inspection by the Regional and Interdepartmental Office of the Environment and the Energy of Ile-de-France (DRIEE) revealed non-conformities with regard to classified industrial facilities for environmental protection. This prompted the Franco-American firm to call on SADE, which it identified thanks to its brand-new website!

The survey submitted by the Paris Regional Division, together with SADE Engineering, proposed three costed solutions to resolve these non-conformities (particularly in relation to the storage of 350m³ of water):

  • installation of a concrete-encased retention pond,
  • installation of a pipe culvert,
  • creation of surface storage around the site.

Following 3D modelling of the site’s terrain, the third solution was ultimately selected. Teams from the Ivry Agency then got involved to install a 30cm-high, 40m-long pond at the back of the site, which provides a maximum flooding depth of 20cm for the site and completely safe access for emergency teams.

The work, which included the installation of shutters in the existing site network, was completed in 10 days in a complex environment (presence of storage containers full of chemical products close by).

Another satisfied – and now compliant – customer!

CONTACT

Upcoming project? Ongoing worksite? Urgent work that needs to be done? Technical issue? Support request? Do you just need some advice or information, or perhaps you’ve got an improvement to suggest? Click here and we’ll quickly get back to you!

FOLLOW US

23-25 av. du Docteur Lannelongue
75014 Paris

  • IN BRIEF
    • Profile
    • Anchoring
    • Path
  • PROFESSIONS
    • Systems
    • Infrastructure
  • SERVICES & SOLUTIONS
    • Regional authorities
    • Industries
    • Major infrastructures
  • REFERENCES
  • CSR
  • APPLICATIONS
  • NEWS
  • CONTACT

Legal notice Ι Anticorruption code of conduct Ι Occupational gender equality index Ι Personal Data Protection Policy Ι Suppliers relationship © 2021 All rights reserved