50km laid in 6 months and 7km in 3 months at the peak of the COVID crisis!
And one…
SADE Morocco reinforced 50km of ⌀ 300 to 400 PVC drinking water pipes in just 6 months for APDN (Agence pour la Promotion et le Développement du Nord, i.e. agency for the promotion and development of Northern Morocco). The project was costed and won during lockdown despite limited consultation. The aim of this project is to secure the drinking water supply of the town of Targuist from the new desalination plant in the town of Al Hoceima.
Located at the heart of the Rif, Targuist is one of the most densely-populated urban centres in the province of Al Hoceima. It has a population of more than 14,000.
And two…
As part of works to bolster raw water production from the future Kharroub dam, SADE Morocco laid 7km of ⌀ 1,200 coated steel pipes to connect the dam’s reservoir to the El Hachef treatment plant for ONEE. This works were completed in three months, particularly using double slide rail shoring in a swampy setting, meaning it absolutely had to be finished before the rainy season hit.