Categories for Uncategorized

SADERTELEC, is constructing the 90 kV underground connection for the future Larivot bioenergy power plant

21 April 2026
SADERTELEC, has been selected by EDF SEI Guyane to carry out the dual underground 90 kV cable circuit connection between the future Larivot bioenergy power plant – scheduled for commissioning at the end of 2026 – and the existing electricity grid serving the Cayenne area. This strategic project contributes to the development of the local energy mix while improving the security of electricity supply across the territory. A strategic power artery The contract covers 3.6 kilometres of dual underground 90 kV cable circuit connection between the interconnection and metering substation at the power plant and the Larivot cable sealing end… +